Building Our Future & Legacy

HTCI Temple 2026-2027 Expansion Project

As our Indianapolis Hindu community grows, so does our spiritual home. Discover our vision to renovate and expand HTCI's facilities to serve the next generation.

HTCI Logo

Hindu Temple of Central Indiana (HTCI)

Fundraising Status as of July 22, 2026

Donated
$673,650
Pledged
$543,157
Goal
$7,000,000
Total Progress: $1,216,807 (17.4%)

Downpayment Secured: $1,400,000 CD in Bank (20%)

Guaranteed Max Price (GMP): $6,799,800 (Pepper Construction)

Architectural Blueprint

First Floor Addition & Renovation Floor Plan

Visual details from American Institute of Architects (AIA) Document A107 showing the expansion and renovation layout. Click on the floor plan to inspect it in high resolution.

Expansion Scope

The 7 Major Project Components

Our expansion is designed to resolve capacity constraints, safety codes, and site drainage.

Larger Dining Hall

3,029 sq. ft. | 275-Seat Capacity

Expanded dining space to comfortably accommodate devotees during peak festivals, annadanam, and major events. Improves crowd flow and reduces wait times during high-attendance days.

Serving Area

1,736 sq. ft. | Up to 250 Capacity

Dedicated serving area designed to efficiently accommodate prasadam and meal distribution. Supports future catering needs, festival-scale operations, and includes expanded dry and cold storage.

Renovated Kitchen Area

1,628 sq. ft. | Heavy Volume Cooking

Renovation and expansion of the existing kitchen to support higher food-production volume. Addition of a dedicated Naivedyam Room for preparing prasad exclusively for the Worship Hall.

New Gift Shop

297 sq. ft. | Puja & Devotional Items

A beautiful dedicated space to offer puja items, vastrams, and devotional materials. Enhances devotee convenience and supports temple fundraising.

New Storage Barn

5,000 sq. ft. | 50' x 100' Facility

Purpose-built facility to house the future Temple Chariot (Ratham), Deity Vahanas, puja materials, festival items, and essential operational equipment.

Ring/Loop Road

360° Fire & Safety Access

Provides unobstructed 360-degree access around the temple for fire trucks and emergency vehicles, satisfying all required modern safety codes.

New Retention Pond

25,000 sq. ft. | 3.10 Acre-Feet Capacity

A new retention pond as part of the Southeast Expansion to meet current building and drainage codes. Holds 3.10 acre-feet of stormwater for effective site drainage and flood control.

Timeline

Construction Timeline

Our schedule is set to have the facilities ready for the June 2027 Jeernodhara Maha Kumbhabhishekam.

July 4, 2026

Bhoomi Puja

Completed
July 24, 2026

Finalize Construction Loan

Secure financing with First Financial Bank

Completed
July 27, 2026

Finalize GMP Contract

Guaranteed Maximum Price contract with Pepper Construction

Completed
August 2026

Permit Approvals

Get all site and building permits approved

Planned
Fall 2026

Sitework Begins

Planned
Winter 2026

Building Construction Starts

Planned
Spring 2027

Interior and Indian architecture work begins

Planned
April 30, 2027

Completion Day

Planned
June 2027

Maha Kumbhabhishekam

Jeernodhara Maha Kumbhabhishekam & Facility ready for use

Planned
Ways to Support

Devotee Giving & Tax Guidelines

Maximize the impact of your donation using these secure giving channels and modern tax advantages.

Please check with your employer to see if they offer donation-matching benefits for contributions made to our Temple.

Cash, Check, or Credit/Debit Card Contributions

Traditional monetary donations are always welcome and may be deductible depending on your individual tax situation.

Automatic Bank Payment

You can set up an automatic monthly payment by signing the ACH/Debit direct authorization form.

* For check donations, please make checks payable to HTCI with "Expansion Project" in the memo field.

Q&A Details

Frequently Asked Questions

Find detailed explanations regarding the scope, timing, budget, funding, and goals of our project.

If you have any additional questions about the Temple Expansion Project or need assistance with the donation format, please feel free to email construction@htci.org.